Horizon Room kitchen expansion construction schedule

Week 1 – June 5

Demolition the walls, construction new wall, grind concrete flooring and electrician to begin

Week 2 – June 12

Finish new wall texturing, move existing walk-in cooler and freezer to new location, and new equipment to arrive

Week 3 – June 19

New hood to arrive and be installed with all mechanical equipment

Week 4 – June 26

Fire sprinklers to be in-lined, ceiling grid work installed, plumber for gas and water hook-ups, an all other mechanical, electrical work to begin

Week 5 – July 3

Electrical work and plumbing to continue

Week 6 – July 10

Seal flooring and cure

Week 7 – July 17

Install new equipment and test

Week 8 – July 24

Install new equipment and test

Week 9 – July 31

Schedule final inspections

Week 10 – August 7

Begin moving inventory and supplies back into kitchen

Clean dining and bar area